Without boring you with details here is the summary of my calculations on what savings I believe JPS is likely to see once the plants mentioned in the previous post are up and running. Figures below are in US$
Annual savings (ADO – LNG Bogue 120 mW) | $ 134,537,321 |
Annual fuel savings (HFO- LNG-190 mW) | $ 89,918,562.57 |
Saving per annum replacing 85mW HFO with Coal ( Jamalco) | $ 65,208,920.64 |
Total fuel savings- fuel switching | $ 301,194,797 |
Working out how much the end user will see ie me and you is a lot more tricky and will require a lot more work than I was able to do just now. I will however by working on something and should have a rough estimate once I have more information in the coming weeks.